Flood Control Fiasco: ₱95-Million Project in Leyte Raises Questions About Governance and Accountability

Spread the love

by Miriam G Desacada

Tacloban City-  Merida Leyte  Mayor Rolando Villasencio has raised serious concerns about a ₱95-million flood control project in Barangay Puerto Bello, which was declared 100% complete despite being far from finished. Here are the key issues with the project 

According to the DPWH website showed the project was completed in July 2024, but actual work only began in August 2024.

However , in an inspectiob conducted by Mayor    Villasencio confirmed the site was still under construction.

Lack of Transparency:

 The DPWH district engineer refused to provide key documents, such as program boards and plans, claiming they were forwarded to the central office.

Seventy (70%)  percent of the project’s budget was released on May 12, 2024, during the election period when government projects were restricted.

 Puerto Bello Village was declared “completed” but remains non-operational due to poor placement and lack of accessibility.

Villasencio has urged the Department of the Interior and Local Government to conduct a comprehensive investigation into the project. This incident echoes similar controversies surrounding flood control projects in the Philippines, including substandard Construction Other flood control projects have been criticized for poor quality, with some collapsing or failing to function as intended.

Corruption Allegations:

There have been allegations of corruption, overpricing, and irregularities in government-funded flood control projects.

This time the said Local Chief Executive Calls for AccountabilityVarious groups, including business organizations and civil society, have demanded greater accountability and transparency in infrastructure projects.

In response to these issues, the government has initiated investigations and proposed reforms, such as aggregating flood control projects within single river basins to ensure technical, environmental, social, and economic viability .

  • Related Posts

    VSU Wins 2025 Tanglaw Award as Philippines’ Top Research Institution

    Spread the love

    Spread the loveby Lemy Macantan The Visayas State University (VSU) has once again proven its excellence in research and innovation as it received the 2025 Tanglaw Award from the Department of Science and Technology–Philippine Council for Agriculture, Aquatic, and Natural Resources Research and Development (DOST-PCAARRD) on January 30, 2026, at the SMX Convention Center, Pasay City, during the 53rd PCAARRD’s Anniversary Celebration. The award recognizes VSU as the Most Outstanding Research Institution, highlighting its vital role in turning scientific knowledge into real solutions that benefit communities and the environment. VSU topped other institutions by achieving remarkable points on technologies developed/utilized, significant information gathered and applied, generated financial resources for the past five years, capability building, and other accomplishments such as institutional publications, awards received, linkages forged, and projects implemented. Along with a trophy, VSU also received a Php5-million grant to support the university’s research, development, extension, and innovation (RDEI) infrastructure upgrading, and capability building. A Century of Purpose, A Culture…

    Borongan Budget Standoff: JO suspension entangled in law, leadership transition, and alleged political delay

    Spread the love

    Spread the loveby Rowel Montes The temporary suspension of Job Order (JO) workers in Borongan City, announced on January 30, 2026, by the Office of the City Mayor through Acting Mayor Emmanuel Tiu Sonco, has continued to stir public debate—now further complicated by allegations surrounding the delayed action on the proposed 2026 annual budget. Budget submission and alleged inaction The Office of the City Mayor, under Mayor Jose Ivan Dayan Agda, formally submitted the proposed Annual Budget for Fiscal Year 2026 to the Sangguniang Panlungsod on October 16, 2025. However, the budget was enacted only on December 23, 2025, leaving the city to operate under a re-enacted budget at the start of the new fiscal year. It is now being alleged by some sectors that the then Vice Mayor—who presided over the Sangguniang Panlungsod at the time—deliberately failed to act promptly on the proposed budget. This perceived inaction, critics argue, may have contributed to the fiscal bottleneck now affecting hundreds of Job Order workers and…

    Leave a Reply

    Your email address will not be published. Required fields are marked *